Construction-related
Doureki Kogyo, Co., Ltd.
Pavement work in the Aikokuhigashi area
Road and River Section, Urban Development Department, Kushiro City
Commendation for Outstanding Construction Project
Construction period
From July 30, 2014, to October 30, 2014
Outline of the construction
Width of the construction site = 5.60 m Length of the construction site = 175.40 m
Civil engineering work : one set Roadbed construction : one set Pavement construction : one set Water drainage construction : one set Road facility installation : one set
Structure removal work : one set Temporary construction : one set
Reason for the award
This construction project included pavement replacement work on a road in the Aikokuhigashi area, part of an annual contract for construction. The construction site was situated in an urban area, particularly in a densely populated residential area.
In two weeks, 28 new drainage basins (excavating 1.5 m to 2.0 m, at a rate of two units per day) were constructed. Road improvements were completed within one week, followed by unevenness correction and pavement work finished in three days. Additionally, because of the presence of only one branch road along the 175-meter stretch, it was challenging to divert vehicles, so residents were thoroughly informed and consulted in advance. Since vehicular traffic was closed during construction, the project was completed without any complaints or problems, thanks to rigorous safety management and daily communication with residents.
During drainage construction, unknown pipes were discovered daily. The contractor promptly communicated with government officials and responded to construction supervisors accordingly. These efforts ensured the construction was completed on schedule without any delays.