Construction-related

Asahi Industries Co., Ltd.

Pavement work at Saiki, the Higashi Kyushu Expressway

Kyushu Branch Office, West Nippon Expressway Company

Safety Council Award

Construction period

From December 28, 2013, to April 21, 2015

Outline of the construction

Volume of road excavation = 39,400 m³  Volume of waste soil excavated = 17,656 m³

Length of precast culvert work = 69.1 m

Area of granular roadbed construction = 23,388 m²  Weight of asphalt mixture = 8,148 t

Water drainage work : one set  Traffic safety facility installation : one set  Traffic management facility installation : one set  Traffic sign installation : one set

Reason for the award

This project included constructing pavement for a new section of the Higashi Kyushu Expressway. Because of the predetermined opening date of the Expressway, there was a need to shorten the construction period for this project. The contractor, NEXCO, and the Ministry of Land, Infrastructure, Transport, and Tourism held extensive meetings to discuss the construction procedure. During these meetings, suggestions were actively proposed, such as replacing on-site concrete casting with prefabricated concrete products for concrete structures. These changes significantly contributed to shortening the construction period, resulting in the project being completed successfully about one month before the scheduled opening day. Up to six teams worked simultaneously on the construction, extending the accident-free construction hours to 100,000. This achievement resulted in a high evaluation score.

Photo of the site
Photo of the site