Construction-related
Tohoku Nichireki Construction, Co., Ltd.
Pavement repair work in Yonekawa, Public Road Disaster Preparedness and Safety Work No. 19-87-A01 in FY 2016
East Civil Engineering Office, Miyagi Prefecture
Commendation for Outstanding Construction Project
Construction period
From October 25, 2016, to February 21, 2017
Outline of the construction
Area of road surface milling = 4,080 m2 Area of on-site base course recycling construction = 3,980 m2
Area of binder course construction = 4,080 m2 Area of surface course installation work = 4,080 m2
Reason for the award
Construction assessment score: 87 points
Because of the winter conditions, snow cover was expected to delay progress and affect the quality of the roadbed. Therefore, a process involving milling, on-site renewal, and binder course installation was planned as a cycle. Furthermore, ground level variations were minimized during the construction period to ensure smooth traffic flow. As the construction area covered in each cycle became smaller, it was expected to increase the number of joints, resulting in uneven ground. To address this, daily progress checks were rigorously conducted to ensure a smooth surface finish. Despite the winter construction period, quality and progress management were effectively implemented, allowing the project to proceed without accidents or delays. These accomplishments were recognized with an award.